Technip- Barracuda: Unloading/loading 4 reels

Early October 2020 four Barracuda reels arrived on a heavy lift vessel a few weeks before Technip’s Deep Star was scheduled to receive them on their deck for deployment in Trinidad. We offloaded the four reels (345mt, 345 mt, 336 mt, 290mt weights) loaded with flexibles and another 100 project packages and crates from the […]

MWCC- Replacing Dunnage

Core manufactured new concrete mats to be placed under four reels in the MWCC dock storage area. When the matts were prepared, Core used the H/L crane to walk the four 200 ton reels with flexibles to temporary storage. We removed the old dunnage and replaced it with new concrete ones. Core then lifted and […]

SS7- Island Victory

Island Victory arrived to Core Industries in September 2020 to load out the mooring chains for the Mad Dog project. This vessel is specialized in receiving chain into its winch system and storing it below deck for deployment in the Gulf at the project site. Core loaded long, heavy (bundles of 127,000 lbs.) shots of […]

MWCC: Receiving two subsea cooling modules

Marine Well Containment Company (MWCC) is responsible for the maintenance, deployment and operation of the Containment System during a response to a deepwater well control incident in the U.S. Gulf of Mexico. MWCC utilizes the facilities and services of Technip USA and Core Industries to store, maintain and test the equipment in Mobile, Alabama. In […]

Mad Dog 2: Loading out 12 Suction Piles

In August 2020 Core loaded out 12 of the Holdback and Mooring Suction Piles that were brought to Core in July 2020. Core first installed the vertical and horizontal lift rigging. Then made preparations to the piles such as, opening valves and installing deployment tools onto them. Our 660-ton crane lifted the piles, adjusted the […]

Receipt and Storage of Holdback and Mooring Piles

In July 2020 Core received 15 Holdback and Mooring Suction Piles. This scope of work included unloading the piles from a vessel and moving them into our dock storage space. The pile weights were from 110 MTs to 252 MTs each. Some of the suction piles had to be twin crane lifted to storage. Core […]

Talos Umbilical Reel

In June 2020 Core Industries offloaded a 350 Metric Ton reel from a Derrick Barge and staged it in our dock storage area. Core loaded the reel onto the Seven Pacific for installation Subsea.  We then unloaded the empty reel from the Seven Pacific. We will load the empty reel onto a barge for return […]

Shell- Princess Flexible Reels

Core offloaded reels from a vessel using the 850 T Heavy Lift Crane and staged them on the dock. The scope of work included removing the packing from the end terminations and installing new lubricants, seals, orings and Handling Heads on each. The Handling Heads provide a means for the Flexible Pipes to be lifted […]

Unloading Fertilizer Barge(s)

Nutrien Ag Solutions commissioned Core Industries to unload fertilizer barges to trucks. Trucks were provided by the customer. The job took one day to complete. Core Industries is known for their ability to handle all types of break bulk material.

Ilenao: Offloading Clinker

In April 2020 Core offloaded 44,000 Metric Tons of clinker to barge using our Piner Smag buckets. The job was completed in 3 days. Core provided all of the labor and equipment including crane operators, flaggers, track hoe’s and operators.