Shell- Princess Flexible Reels

Core offloaded reels from a vessel using the 850 T Heavy Lift Crane and staged them on the dock. The scope of work included removing the packing from the end terminations and installing new lubricants, seals, orings and Handling Heads on each. The Handling Heads provide a means for the Flexible Pipes to be lifted […]

Unloading Fertilizer Barge(s)

Nutrien Ag Solutions commissioned Core Industries to unload fertilizer barges to trucks. Trucks were provided by the customer. The job took one day to complete. Core Industries is known for their ability to handle all types of break bulk material.

Ilenao: Offloading Clinker

In April 2020 Core offloaded 44,000 Metric Tons of clinker to barge using our Piner Smag buckets. The job was completed in 3 days. Core provided all of the labor and equipment including crane operators, flaggers, track hoe’s and operators.

Suction Pile Loadout: February 2020

In February 2020 Core loaded out one (110 ton) suction pile to the Harvey Provider for Subsea Seven. The suction pile had been in storage since late December along with 6 more. Core will approximately have 22 piles stored at our dock before this project is complete.

Saipem Constellation: Loading Reels

January 2020 Saipem Constellation vessel arrived at Core Industries to retrieve the four (917 ton) reels and one (175 ton) top module from our storage yard. The reels and top module were previously brought in August 2019. SPMT’s (Self Propelled Mobile Transporters) were used to move the reels from their POR (place of rest) and […]

Discharging Copper Slag

In January 2020 Core Industries discharged 50,000 tons of copper slag. Copper slag is a material commonly known as black beauty or sandblasting sand. The slag was discharged into hoppers, loaded into trucks and transported to Mobile Abrasives. Core provided all the necessary facilities, personnel and equipment to discharge the copper slag efficiently and economically.

December 2019: Sider Jasmine

Sider Jasmine arrived at Core Industries private port facility in December 2019 delivering 7 suction piles for the Mad Dog 2 project. Core offloaded and stored the suction piles. The suction piles will be picked up at a later date. Core’s storage capabilities and proximity to the Gulf of Mexico allows us to assist in […]

SPI/Mobile Pulley Works: A-Frame Loadout

After a successful dredge ladder loadout in early November 2019, SPI/Mobile Pulley Works contracted Core to utilize and load out an A-frame onto a barge for delivery to their client. Berard transported three A-frame parts from SPI/Mobile Pulley Works to Core’s private port facility. Core worked alongside, providing crane services and other critical assistance, MPW […]

SPI/Mobile Pulley Works: Dredge Ladder Loadout

In November 2019 SPI/Mobile Pulley Works utilized Core Industries private port facilities to load out a dredge ladder and other associated pieces weighing in excess of 300 tons. Berard transported the dredge ladder approximately 3 miles from the SPI facility to Core Industries in Theodore, AL. Once the ladder was received at the port, it […]

September 2019: Shell Mars A TLP Drilling Riser Load Out

Shell awarded a contract to Core Fabrication, LLC (Core) to refurbish and load out the drilling riser string dedicated for the Mars A Tension Leg Platform located in the Gulf of Mexico. Core’s scope of work included OD and ID cleaning, inspection of seal surfaces and buoyancy modules, application of rust preventative on the ID […]